A moisture survey should answer a defined roofing decision—not produce a colorful image and a vague conclusion. Infrared imaging, electrical-impedance scanning and core cuts measure different things, work under different conditions and carry different limitations. The useful question is not “Which method is best?” It is “Which evidence can support this decision on this assembly?”
The direct answer
Use nondestructive survey methods to locate suspect areas, then verify representative findings invasively before quantities or scope are treated as confirmed. No universal wet-area percentage decides whether a roof can be coated, recovered or replaced. Assembly type, deck condition, attachment, code, manufacturer requirements and the decision being made still control.


Start with the decision the survey must support
- Coating or restoration: Where are suspect materials, how will they be verified and removed, and does the remaining assembly qualify under the written system requirements?
- Recover: Can retained materials serve as a suitable base after wet or unsound components are addressed?
- Tear-off: What evidence supports demolition limits, allowances and unit pricing?
- Leak investigation: Is the goal to map affected materials, locate a membrane breach, or trace an entry path? Those are different tasks.
- Acquisition or capital planning: What uncertainty remains, and what additional verification is needed before a budget decision?
Infrared imaging: locate thermal anomalies under the right conditions
ASTM C1153-23 covers infrared imaging used at night to locate wet insulation in qualifying roofing systems with insulation above the deck and in contact with the waterproofing. The practice addresses equipment, weather, construction effects, operating procedures and invasive verification.
Infrared does not “see water.” It records surface-temperature patterns that may be consistent with retained heat in affected materials. Weather, solar loading, wind, surface conditions, ballast, deck type, insulation, recent rain and interior conditions can change the signal. ASTM also states that the practice does not determine the moisture cause or point of entry.
Infrared is strongest when
- the assembly and weather conditions support a usable thermal differential;
- the operator documents survey conditions and roof construction;
- anomalies are mapped rather than treated as confirmed quantities; and
- representative locations are verified with invasive testing.
Electrical impedance: compare readings across compatible assemblies
ASTM D7954/D7954M-22a covers nondestructive electrical-impedance scanning for comparative moisture surveying in compatible roofing and waterproofing systems. It can support installation checks, maintenance, condition assessment and repair or replacement planning.
Compatibility matters. Conductive surfaces or near-surface metallic components can distort readings. ASTM identifies limitations involving metal, black EPDM, foil-faced materials and protected assemblies with overburden. A scanner reading is comparative evidence, not a laboratory moisture-content result or automatic cause finding.
Impedance is strongest when
- the membrane, insulation, deck and nearby materials are compatible with the method;
- the report identifies the scanning technique, calibration and survey grid;
- known assembly changes are separated from suspected moisture responses; and
- core samples verify representative high and control readings.
Core cuts: direct evidence at selected points
A core cut can confirm the roof layers and conditions at one location. It can identify membrane and insulation layers, reveal visible moisture or deterioration, support thickness verification and provide material for additional evaluation. It does not describe the entire roof unless the sampling plan is defensible.
Every cut must be located, photographed, logged and permanently repaired with a detail compatible with the existing system. The plan should include representative anomalies, control areas and locations tied to the actual decision. If a report lists cores without explaining why those points were selected, the evidence is harder to use.
What a decision-grade moisture report should contain
- roof-area plan, assembly information and known changes in construction;
- date, time, weather and surface conditions;
- equipment, calibration and survey method;
- mapped anomalies and a clear legend;
- verification locations, photographs and observed layer conditions;
- limitations, inaccessible areas and conditions that may affect readings;
- a distinction between measured observations, verified findings and professional interpretation; and
- repair documentation for every invasive opening.
How findings change the roofing scope
A good survey does not force one answer. It can narrow repair areas, define removal allowances, identify where more testing is needed, disqualify an assumed restoration path or support a better-defined recover or replacement scope. The final decision still depends on code, approved assemblies, deck and attachment conditions, drainage, detailing and written manufacturer requirements.
For the broader decision, use OGC’s repair, coating and replacement framework, recover-versus-tear-off guide, inspection scope and condition-documentation kit.
Scope boundary
This guide is planning information. It does not represent a project-specific survey, engineering conclusion, code interpretation or manufacturer acceptance. The required method, operator qualifications, verification plan and report should be defined for the actual assembly and decision. OGC will confirm its roofing scope and whether specialist testing is required after reviewing the property.